| Measure | Typical trigger | Disruption | Who controls it in a leased building | Evidence needed |
|---|---|---|---|---|
| Operational (schedules, setpoints, recommissioning, fault detection) | Any time | Low | The tenant, if it controls the building management system | Metered before/after trend data |
| Lighting and controls | Any time, or at a lease event | Low to medium | Depends on the base-building vs. tenant fit-out split | Metered consumption before/after; equipment spec sheet |
| Envelope and equipment replacement | At end of life | Medium to high | Usually the landlord, for base-building systems | Asset age and condition; engineering assessment |
| Fuel switching / electrification of heating | At end of life | High | The landlord for central plant; the tenant for standalone units | Feasibility study; available electrical capacity |
| Portfolio consolidation | At a lease event or renewal | High (relocation) | Whoever holds the renew-or-relocate decision | Space, condition and cost assessment across the portfolio |
Buildings, Data and Compliance in Québec
Part 3 of 3
A carbon-reduction roadmap for an occupied portfolio
A carbon-reduction roadmap starts with the baseline
New-build certifications get most of the attention, but they answer the wrong question for a portfolio that already exists. A credible carbon-reduction roadmap starts where disclosure starts: energy metered by building and by fuel, not a portfolio-wide estimate, with each site classified to Scope 1 (fuel burned on site), Scope 2 (purchased electricity) or Scope 3 (other indirect emissions) depending on the lease boundary — a classification question our earlier piece on ESG disclosure and the real-estate line covers in depth. Here, that same baseline becomes the input to a reduction plan, not just a disclosure exercise.
A measure ladder ordered by cost and disruption
Once the baseline exists, the discipline is sequencing, not ambition. Cheaper, less disruptive measures come first, because they are quick to fund and easy to reverse if wrong; capital-heavy measures wait for a natural trigger instead of a target year. The table sets the ladder out, from operational fixes on existing equipment (including recommissioning, which means re-tuning systems to perform as designed) to electrification of heating. The last rung, consolidating into fewer, better buildings, is a decision for portfolio strategy more than for this roadmap.
The chart argues one point: doing nothing does not hold emissions flat, as ageing equipment and rising loads push the index up slightly. Operational and lighting measures bend the curve down modestly and quickly, but the steep drop appears only once heating is electrified — a measure that typically waits for the heating system to reach end of life.
Why electrification works differently in a low-carbon grid
Electrifying heating trades on-site fuel combustion for grid electricity — a trade whose emissions benefit depends entirely on what the grid burns. In Québec, that trade is unusually favourable: hydropower supplied 94% of the province's electricity generation in 2021, and the Canada Energy Regulator put the grid's generation-emissions intensity at 1.2 grams of CO2 equivalent per kilowatt-hour in 2022 — a 68% reduction from 2005 levels and far below Canada's national average of 100 g CO2e/kWh.
The wider boundary is why Hydro-Québec's own life-cycle estimate is higher, at 34.5 g CO2eq/kWh; both figures can change. For a portfolio with sites elsewhere in Canada, the same measure lands very differently depending on the local grid.
None of this makes electrification automatic. Heating-system replacement is capital-intensive, may require new electrical capacity, and competes with other end-of-life priorities. The governance question is whether the roadmap ties the decision to the equipment's actual end-of-life date and a real feasibility assessment — not to a target year alone.
The leased-space problem
A roadmap written for an owned building rarely survives contact with a leased one. In owned space, every lever above is available and the only constraint is capital. Where the tenant controls its own systems, operational and lighting measures are usually available, and fit-out equipment reaches its own end of life independently of the landlord's central plant. Where the landlord controls the systems, the tenant's only lever is contractual: data, cost-sharing and coordination — not the equipment itself.
That is what a green lease clause is for. Canada's national green-lease standard — REALPAC's Office Green Lease, last updated in 2021 — sets out provisions for sharing energy data and aligning cost recovery for efficiency upgrades; it is not mandatory, and a landlord may decline it, but it is a template for the conversation. Before renewing a lease, ask: does it obligate the landlord to share metered energy data, and does it give the tenant visibility into plans for a central system nearing end of life? These are questions for your real-estate counsel, not legal advice offered here.
Sequence to the capital cycle, then track it
The discipline that makes any of this credible is timing capital-heavy measures to the capital cycle, not to a communications calendar. Replacing equipment years before its useful life ends destroys value a wait would have preserved; leaving it years past end of life, already failing inspection, destroys reliability instead. Build the roadmap around each system's actual remaining life, and let public funding offset cost rather than dictate timing — federal programmes such as the Canada Green Buildings Strategy's Deep Retrofit Accelerator Initiative (funded until March 31, 2027 as of November 2026), and Hydro-Québec's Efficient Solutions Program for businesses, both target this kind of retrofit, and both change; confirm current eligibility before relying on either.
Tracking matters as much as sequencing. A roadmap that reports progress against the same metered baseline it started from survives an audit committee's questions; one that resets its baseline every few years to flatter the trend does not. Track it the way you would defend a disclosure number, because eventually it may become one.
Key takeaways
- Most of the buildings an organisation will occupy in 2035 already exist, so the credible roadmap covers occupied, mixed-tenure portfolios — not new-build certification.
- Sequence measures from operational and lighting fixes through to end-of-life equipment replacement and electrification; capital-heavy measures wait for a natural trigger, not a target year.
- Québec's low-carbon grid — 94% hydropower in 2021, a 2022 generation-emissions intensity of 1.2 g CO2e/kWh (Canada Energy Regulator) — makes electrification of heating unusually effective, though the same measure lands differently on grids elsewhere.
- In a leased building, the available lever depends on who controls the systems; a green lease clause is the contractual tool for the landlord-controlled case.
- Track progress against the same metered baseline used to start the roadmap — the same rigour disclosure requires.
Frequently asked questions
Where should a carbon roadmap start?
With a baseline: energy metered by building and by fuel, not a portfolio-wide estimate, plus a lease-boundary classification for each site. Measures are then sequenced against that baseline, not against a target year alone.
Can a tenant reduce emissions in a leased building?
Yes, within the limits of what it controls. A tenant typically controls operational measures and its own fit-out equipment; where the landlord controls central systems, the tenant's main lever is contractual — data, cost-sharing and coordination through the lease, ideally a green lease clause.
Should we electrify heating in Québec?
Québec's low-carbon grid makes electrification unusually effective on paper, but the decision still depends on the specific building: available electrical capacity, the heating system's remaining life, and a proper feasibility assessment. Treat this as an engineering question to commission, not a default answer.
Turning a baseline into a sequenced, financeable roadmap is a governance exercise as much as an engineering one — the kind of gap our workplace and ESG governance mandate is built to close, alongside the data and technology benchmarking work that keeps the baseline honest. If your board wants a credible roadmap before the next capital cycle, a confidential conversation is a reasonable step — get in touch.