| Weak KPI | What it actually measures | Replacement KPI | Data source | Independent verifier | Consequence |
|---|---|---|---|---|---|
| Hard services (building systems) — work orders closed on time | Ticket speed, self-reported | Repeat-failure rate within 30 days | Building management system (BMS) equipment logs | Client facilities engineer | Root-cause report; repeats escalate quarterly |
| Soft services (occupant-facing) — tasks completed per schedule | A checklist ticked, not cleanliness | Unannounced walkthrough score | Site visits, photo-logged | Site manager, not the supervisor | Credit below an agreed score |
| Energy & utilities — monthly report filed | That a report exists, not what it says | Metered consumption per m² vs. baseline | Independent submetering, utility invoices | Client energy manager | Variance above tolerance triggers review |
| Security — guard hours per schedule | Presence on paper, not prevention | Verified response time, sampled log | Access-control, camera timestamps | Client security manager | Repeated misses reach the security committee |
| Integrated FM — one blended SLA score | Average hides a failing sub-metric | Each sub-metric reported separately | Raw sub-metric data | Client governance forum | No renewal on the blended number alone |
| Client-side obligations — none tracked | Nothing; only the provider is accountable | Approvals turned around within agreed days | Approval-log timestamps, both sides | Joint governance forum | Client-caused delay excluded from the KPI |
Are You Getting What You Pay For?
Part 4 of 4
KPIs That Measure Nothing: Designing an SLA/KPI Regime That Changes Behaviour
The vocabulary problem: SLA, KPI and KRI
Three terms get used almost interchangeably in a facilities contract, hiding a design flaw. A service-level agreement (SLA) is the promised level of service. A key performance indicator (KPI) is the measure showing whether the SLA is met. A key risk indicator (KRI) is different: a leading signal checked before the SLA is breached — a rising maintenance backlog, say, well before equipment fails. In our experience, contracts carry plenty of KPIs and almost no KRIs, one reason problems surface only once they are expensive.
Watermelon reporting: green outside, red inside
A facilities contract can carry dozens of SLA and KPI measures and report green on every one, month after month, while the buildings it covers visibly deteriorate. Practitioners call the pattern watermelon reporting — green outside, red inside. It rarely happens because anyone is lying; it happens because the measures track what the provider controls and reports, not the outcome the client needs verified.
Figure 1 makes the point with a mock dashboard: the same twelve measures, reported by the provider on the left, and checked independently on the right.
Nothing on the left panel is necessarily false. Each tile reflects what the provider’s own system recorded — and self-reported data can go unverified for years even inside a well-resourced organisation: a 2021 review of Toronto’s Corporate Real Estate Management Division found payments processed without checking the worksite logs or technician certificates behind them. The gap opens the moment someone outside that system checks the same question differently — exactly what a structured contract audit does: work orders checked against reported KPIs, not accepted as given.
Five ways a KPI regime fails
The same design flaws recur across ungoverned KPI regimes, and none shows up in the monthly report:
- Self-reported inputs — the only evidence is the provider’s own system, unchecked.
- Activity, not outcome — counting what was done, not what it produced.
- Thresholds set by the provider — proposed, and rarely challenged, by the party it measures.
- No consequence attached — missing the number changes nothing.
- Too many measures to watch — a large KPI count spreads attention so thin none is reviewed.
The design rule for every KPI
A KPI worth keeping answers seven questions, not one number. Figure 2 lays out the chain each measure should travel, from SLA to consequence, and the shortcut — self-reported data — that breaks it.
For each measure worth keeping, the seven questions are:
- What outcome does it protect?
- What is actually measured, precisely?
- Where does the data come from, and is that source independent?
- Who verifies it, on a cadence the client controls?
- What are the threshold and tolerance?
- What is the consequence when it is missed?
- Which forum reviews it, with authority to act?
The Government of Canada’s Vendor Performance Management Policy, in force since 18 September 2026, backs the fourth question: the client-side technical authority, not the vendor, conducts the evaluation, using a scorecard that covers cost, quality, schedule and management. Federal procurement guidance on incentives asks for objectives that can be measured and verified, and for simple structures. One consequence mechanism is a holdback: payment withheld until a criterion is met. A structured governance framework puts this discipline in place without building permanent internal capacity.
Balance leading and lagging measures: a KRI on a rising work-order backlog is worth more than a KPI on last month’s average, because it gives someone time to act before the outcome is already lost. And keep the list short. A dozen KPIs that are actually reviewed by people with authority to act on them govern a contract better than sixty that nobody reads.
Rebuilding an existing regime without renegotiating everything
An existing contract rarely needs a full renegotiation to fix its KPI regime. Many master agreements allow the measures themselves, as distinct from price or term, to be revised by variation (a formal amendment) or side letter, without reopening the document. Confirm the amendment mechanism with counsel before assuming it is available. Pricing model and KPI regime need to match, too — a fixed-fee contract measured only on activity invites the scope erosion its pricing already incentivises.
The KPI conversation runs the other way too. A provider asked to hit a response-time target needs the client to approve scope changes, grant site access and pay on time — obligations belonging on the same review agenda as the provider’s. A regime measuring only one side of the relationship is measuring the wrong thing.
If your monthly KPI report has never been tested against an independent source, a confidential conversation is a reasonable start.
Key takeaways
- A KPI regime can report green every month while service quality erodes — the sign is a measure tracking what the provider controls, not the outcome that needs verifying.
- Every KPI worth keeping answers seven questions: outcome, measure, data source, verifier, threshold, consequence, review forum.
- A dozen KPIs actually reviewed beat sixty nobody reads.
- Rebuilding a regime rarely needs renegotiating the whole contract — confirm the amendment mechanism with counsel.
- The client has obligations too; measuring only the provider measures half the relationship.
Frequently asked questions
How many KPIs should an FM contract have?
Fewer than most contracts carry. A dozen measures actually reviewed by people with authority govern a contract better than sixty nobody reads; add more only when each earns its place.
What is the difference between an SLA and a KPI?
An SLA is the promised level of service in the contract; a KPI is the measure showing whether it is met. A KRI is related but separate — a leading signal checked before the SLA is breached, not after.
Can we change KPIs in an existing contract?
Often yes, without reopening the agreement: many master agreements allow the measures to be revised by variation or side letter. Whether that exists is specific to your contract — confirm with counsel first.
Who should verify KPI data independently of the provider?
Someone with no stake in the result: a client-side facilities or audit function, or an outside reviewer paid a disclosed fee rather than a commission tied to the outcome.