| Risk category | Example risk | Typical trigger/date | Owner | Evidence |
|---|---|---|---|---|
| Occupancy and lease events | Renewals concentrated in one year | Lease expiry or option date | Operations/facilities | Lease abstract, renewal timeline |
| Supplier and contract | One provider across the portfolio | Contract expiry; provider financial review | Procurement | Contract register, provider financial check |
| Asset condition and deferred maintenance | Repairs past their planned date | Condition-assessment cycle | Operations/facilities | Condition assessment, capital plan |
| Compliance and regulatory | Fire/life-safety or accessibility deficiency | Inspection or correction-order date | Operations/facilities, legal | Inspection report, correction log |
| Physical climate and business continuity | Flood, extreme heat or power interruption | Site vulnerability review | Operations/facilities | Site risk assessment, continuity plan |
| Financial | Cost escalation or currency exposure | Budget cycle; lease renewal | Finance | Escalation clauses, FX exposure schedule |
| Reputational and workplace | Utilisation collapse or safety incident | Utilisation review; incident date | Operations/facilities, HR | Utilisation data, incident log |
Part 3 of 3
The Corporate Real Estate Risk Register: What Belongs on It, and Who Reviews It
What a corporate real estate risk register actually covers
Most enterprise risk registers name strategic, financial, cyber and operational risk. Real estate rarely appears as its own line – when it appears at all, it is folded into “facilities” and reviewed only once something has gone wrong.
A lease expiring in eighteen months, one supplier holding every site’s facilities contract, a fire-safety deficiency past its correction date: each is concrete, dated and ownable – exactly the shape a risk register already expects. A corporate real estate risk register does not need a new committee; it applies the board’s existing risk discipline to the buildings it occupies.
Public-sector real estate governance in Canada already treats this as ordinary practice. Treasury Board of Canada is piloting real property transaction limits set by assessed risk and capacity, weighing a department’s controls and governance against each transaction’s characteristics and parties involved. A private organisation does not need Ottawa’s thresholds; it needs the same habit of pricing risk before it acts.
Seven risk categories, not a folder of anecdotes
A usable register groups risk into a small number of categories, each with a natural home and a natural owner. Seven cover most of what a multi-site portfolio carries:
- Occupancy and lease events – expiries, options and renewals concentrated in a single year.
- Supplier and contract – one provider across the portfolio, an approaching contract expiry, or a provider’s own financial health.
- Asset condition and deferred maintenance – the backlog behind a building’s day-to-day appearance.
- Compliance and regulatory – fire and life safety, accessibility, and, for connected buildings, data obligations under Québec’s Law 25 (see our piece on smart buildings and Law 25).
- Physical climate and business continuity – flood, extreme heat and power interruption.
- Financial – cost escalation, currency exposure on cross-border leases, and effects on loan covenants (the conditions a lender attaches to financing).
- Reputational and workplace – a utilisation collapse, or a safety incident.
Scoring risk: likelihood times impact, not gut feel
A register that just lists risks invites disagreement about which one matters most. Scoring each entry by likelihood and impact, against scales fixed in advance, lets a committee compare a lease expiry to a climate exposure on the same page. The Government of Canada’s guidance on integrated risk management describes exactly this discipline: risk assessed by likelihood and impact, with a corporate risk profile documenting key risks, the response to each, and who is accountable.
The figure below places one illustrative example per cell – not a scored assessment of any real portfolio, but a demonstration that the same nine-cell grid a board already uses for enterprise risk works just as well for buildings.
Ownership and the cadence that keeps the register alive
Every entry needs a named owner, not a department. Where a decision-rights map already exists, the register borrows its owners directly – it is the standing item the map hands to the board once a decision is made and a residual risk remains (see our piece on who owns real estate decisions). Where no map exists yet, assigning an owner to each category above is a reasonable place to start one.
Cadence matters as much as ownership. A workable pattern reviews the register quarterly at the executive committee, annually at the board – where the categories and scales themselves are revisited – and immediately whenever a trigger event fires: a landlord notice, a supplier’s credit downgrade, an inspection failure. A register nobody revisits between board meetings is a document, not a governance practice.
From risk register to decision
A risk register earns its place on the board’s agenda only if each entry leads somewhere: a lease-expiry risk points to the lease-or-renew decision it warns about; a single-supplier risk points to the next re-tender. A risk without a decision path is a worry list, not governance – which is what most real estate risk becomes in a spreadsheet nobody outside the department opens.
Judgement still decides. The register gives it a fixed place to land: the same nine cells, the same seven categories, reviewed on the same schedule, whichever building or contract is under discussion this quarter.
Key takeaways
- Real estate risk is concrete, dated and ownable – lease expiries, single-supplier dependence and deferred maintenance belong on the enterprise risk register, not folded into “facilities.”
- Seven categories cover most of what a multi-site portfolio carries: occupancy and lease events, supplier and contract, asset condition, compliance, physical climate, financial, and reputational or workplace.
- Score each entry by likelihood and impact against scales fixed in advance – it lets a lease expiry and a climate exposure be compared on the same page.
- Review the register quarterly at the executive committee, annually at the board, and immediately on a trigger event – not only once something has already gone wrong.
- A risk without a decision path is a worry list; tie every entry to the decision it is warning the organisation to make.
Frequently asked questions
What risks should a real estate risk register include?
At minimum, seven categories: occupancy and lease events, supplier and contract, asset condition and deferred maintenance, compliance and regulatory, physical climate and business continuity, financial, and reputational or workplace risk. Each entry needs an example risk, a typical trigger or date, a named owner, and the evidence a reviewer would ask for.
Who owns real estate risk in a company?
Ownership should follow whoever already owns the underlying decision – operations or facilities for most categories, procurement for supplier and contract risk, finance for cost and currency exposure. Where a decision-rights map exists, the risk register borrows its owners directly rather than inventing new ones.
How often should the board review property risk?
A workable cadence reviews the register quarterly at the executive committee, annually at the board – when the categories and scales themselves are revisited – and immediately whenever a trigger event fires, such as a landlord notice or a supplier’s credit downgrade.
A risk register tells the board which real estate decisions are coming due, and when. For a confidential conversation about building or auditing a portfolio risk register, get in touch. For how we approach the decisions the register points to, see Portfolio & Capital Strategy and Supplier & Outsourced Services Governance.